Sub-Enclosure No. 2 to Enclosure No. 1 in Despatch No. 302 of the 10th July, 1902.
599
Estimated cost of Kowloon Scheme, including Reservoir, Filter Beds, Mains, Service Reservoir, etc............... $835,000
Do. Do. of Pokfulam Scheme including Reservoir, Pumping Station and Machinery, Mains, etc., this is a mere guess at present.. $1,000,000
Do. Do. of Reservoir in progress at Tai Tam. $120,000
Projected Waterworks to be taken in hand now.
Pumping Engine and Main to Peak, say, $50,000 Reconstruction of No. 2 Tank, say, $20,000 Service Reservoir in progress on Mount Gough. $23,000 Introduction of Meters and Fountains in City, say, $133,000 Total $2,131,000Several of the estimates given above are mere guesswork, but I think they may be regarded as minimum figures.
20th June, 1902.
(Sd.) W. Chatham.
}
ཧཱུྃ
÷
Sub-Enclosure No. 2 to Enclosure No. 1 in Despatch No. 302 of the
10th. July, 1902.
599
Satinated cost of Kowloon Scheme, including Reservoir, Filter Beds, Maina, Service Reservoir, ko...............
$835,000
C
Do.
Do.
of Faitas Tuk Scheme including Reservoir, Pumping Station and Machinery, Maina, đo., this is a mere guess at present..La
.1,000,000
Do.
Do.
of Reservoir. in progress at
Taitan.
120,000
Projected Waterworks to be taken in hand now. Pumping Engine and Main to Peak, say, Reconstruction of No. 2 Tank, say,............. Service Reservoir in progress. on Mount Gough.... Introduction of Meters and Fountains in City, say,
50,000
20,000
23,000
Total...
...................... 133,000 $2,131,000
Several of the estimates given above are mere guesswork, but I think they may be regarded as minimum figures.
20th. June, 1902.
(Sd.) W. Chathau.